Concrete Spall Repairs at Terminal 2 Roadways, Daniel K. Inouye International Airport

Progress

DesignMar 8 2021
ProcurementFeb 8 2024
Pre-ConstructionJul 5 2024
ConstructionMar 1 2025
Project Acceptance / PunchlistApr 23 2026
Post-ConstructionTBD

Project Scope

Concrete repairs to spalling, delaminated, and cracked concrete, expansion joint repairs, waterproofing improvements, drainage improvements (drain inlet relocation, trench drain replacement, drain pipe replacement/rerouting), fixed planter removal and replacement with concrete sidewalks, and lighting and electrical improvements at the Terminal 2 Departures and Third Level Roadways and the Ewa and Diamond Head Concourses Second and Third Level Roadways.

Progress Updates

Notice to Proceed for pre-construction activities is set for March 1, 2025.