Overseas Terminal Roof Replacement, HNL

Progress

DesignAug 6 2018
ProcurementNov 10 2021
ConstructionMar 28 2023
Project Acceptance / PunchlistJun 30 2025
Post-ConstructionTBD

Project Scope

Roof and roof drainage repairs above the Terminal 2 facilities spanning between the Ewa Group Tour Area to the west, to the Diamond Head Group Tour to the east. Other ancillary work involves concrete/CMU spall repair, structural steel repair, stairway repairs and/or replacement, mechanical work, and electrical work.

Progress Updates

Construction anticipated to be complete in June 2025.