Restroom Improvements, KOA
Progress
DesignJul 23 2018
ProcurementJan 31 2022
ConstructionOct 3 2022
Project Acceptance / PunchlistApr 30 2025
Post-ConstructionTBD
Project Scope
Renovation of the interior of the existing North and South Terminal restroom buildings on the secure airside; building two (2) new restroom buildings adjacent to existing restrooms on the secure airside; . Construction of a hard-covered walkway connecting the Central Security Checkpoint to the airside restrooms to the North and South.
Progress Updates
Construction ongoing.
Tentative project completion in Q2 2025.