Restroom Improvements, KOA

Progress

DesignJul 23 2018
ProcurementJan 31 2022
ConstructionOct 3 2022
Project Acceptance / PunchlistApr 30 2025
Post-ConstructionTBD

Project Scope

Renovation of the interior of the existing North and South Terminal restroom buildings on the secure airside; building two (2) new restroom buildings adjacent to existing restrooms on the secure airside; . Construction of a hard-covered walkway connecting the Central Security Checkpoint to the airside restrooms to the North and South.

Progress Updates

Construction ongoing.

Tentative project completion in Q2 2025.